The A-5 and M-30 will have no direct connection until 23 December

The A-5 and M-30 will not have a direct connection from 10 November to 23 December. EMT will reinforce its lines by up to 25% during the closure.

Alberto Sanz
Alberto Sanz
· 3 min read

The connection between the A-5 and the M-30 will be closed to traffic in both directions from Tuesday 10 November. The closure, lasting 43 days, will allow for the completion of the motorway's underground section.

The connection between the A-5 and the M-30 will remain closed to traffic in both directions from Tuesday 10 November until 23 December, for a total of 43 days. According to Noticias para Municipios, the closure will facilitate the final works of the motorway's underground section and link the new tunnel with the underground infrastructure of the M-30.

Drivers who use the A-5 as their main access to the capital, especially from the municipalities in the southwest of the region, will notice the change in their journeys. While the works are ongoing, the surface section will remain open with two lanes in each direction, but direct access to the M-30 tunnels will be interrupted.

The City Council of Madrid recommends using the M-40 as an alternative bypass, with links via the A-42, A-6, and M-503. For long-distance journeys, it also suggests routes via the M-45, M-50, and R-5.

To compensate for the closure, the City Council and the Regional Transport Consortium have prepared a public transport reinforcement. The Municipal Transport Company (EMT) will increase the fleet of lines 31, 36, 39, 138, and 158 by up to 15.4% on weekdays between 10 and 26 November, with intervals of between half a minute and a minute and a half.

From 27 November until 23 December, the reinforcement will reach 25%, both on weekdays and on Saturdays and holidays. On weekends, line 33, which serves Casa de Campo, will also be added, and there will be reserve vehicles for night services, especially on line N19. The SE2 shuttle service between Plaza Elíptica, Aluche, and Cuatro Vientos will also be maintained, along with the free circular line SE3 between Batán and Lucero.

Metro de Madrid will keep its entire fleet available on lines 3 and 10, with the possibility of adding trains on line 10 from Puerta del Sur. In intercity transport, the lines connecting the capital with Móstoles, Alcorcón, and Navalcarnero may add larger capacity buses. The City Council is also considering adding a train on the C-5 branch between Móstoles and Embajadores, pending confirmation from Renfe.

The operation will coincide with the works that Adif will begin on 11 November between Villaverde Alto and Atocha. These works will require the termination of the Atocha-Humanes train service on the C-5 at Villaverde Alto.

During the closure, the 172 metres that separate the new A-5 tunnel from the existing one on the M-30, at the height of avenida de Portugal, will be joined. The works include demolishing the current ramp, excavating around 7,000 cubic metres of earth, and installing 128 prefabricated beams, which will be added to the 14 placed in summer to complete the planned 142.

Afterwards, a compression slab will be executed, requiring around 1,000 cubic metres of concrete, and the waterproofing of the cover will be completed. According to municipal estimates, the underground section will allow for the relocation underground of 90% of the approximately 80,000 vehicles that travel daily on the surface of the A-5.